Fleischmann Construction Company Et Al. v. United States To The Use Of Forsberg Et Al.

• 1925 • 270 U.S. 349 • Taft Court
In the case of Fleischmann Construction Company et al. v. United States to the Use of Forsberg et al., 1925, a dispute arose over payment for work done on a federal construction project. The plaintiffs were subcontractors who had not been paid by the primary contractor and sought compensation from both the contractor and its surety company under provisions in their contract that required them to pay all laborers and suppliers involved in the project. The Supreme Court ruled against Fleischmann...Open Case
Score:
Copyright © 2026Etalia.ai All Rights Reserved
  • Blog
  • •
  • Privacy
  • •
  • Terms
1 results found
Become a Sponsor
Support Us
Feedback: We can do better!

Your feedback is extremely important to us and greatly appreciated.
Tell us what went wrong

Copied to clipboard
StarredCase saved
Oh No!
Chief Taft Court
Term: 1925
Docket: 50
270 U.S. 349
46 S. Ct. 284
70 L. Ed. 624
1926 U.S. LEXIS 415
Argued: Oct 15, 1925

Fleischmann Construction Company Et Al. v. United States To The Use Of Forsberg Et Al.

  • Pro
  • Pro
Go Pro!orto acess these features and extra content.

Opinion Summary
AI Abstract

In the case of Fleischmann Construction Company et al. v. United States to the Use of Forsberg et al., 1925, a dispute arose over payment for work done on a federal construction project. The plaintiffs were subcontractors who had not been paid by the primary contractor and sought compensation from both the contractor and its surety company under provisions in their contract that required them to pay all laborers and suppliers involved in the project. The Supreme Court ruled against Fleischmann Construction Company, holding that these contractual provisions created an obligation for both parties to ensure all workers were compensated regardless of whether they directly contracted with those individuals or companies themselves. This decision established important legal precedent regarding liability within complex contractual relationships, particularly as it pertains to federally funded projects.

Dissent Summary
AI Abstract

The dissenting opinion in Fleischmann Construction Company et al. v. United States to the Use of Forsberg et al., argued that the majority's decision was inconsistent with previous rulings and misinterpreted the Miller Act, a federal law providing payment protections for subcontractors working on public construction projects. The dissent contended that under this act, a general contractor is required to provide a surety bond guaranteeing payment for labor and materials used by subcontractors; if they fail to do so, they are liable for any unpaid claims from these parties. In this case, however, the majority ruled against Forsberg (the subcontractor) who sued Fleischmann (the general contractor) over an unpaid claim because he did not directly contract with them but rather through another entity acting as middleman between both parties. The dissent believed this interpretation unfairly limits protection only to those who have direct contractual relationships with general contractors despite language in the Miller Act suggesting broader coverage.

Opinion written by Justice ETSanford
Decided: Mar 01, 1926
PDF viewer is not available.
Go Pro!orto acess these features and extra content.
Related Cases
AI Assist
Go Pro!orto acess these features and extra content.
PDF viewer is not available.
Oral Transcripts
Go Pro!orto acess these features and extra content.
Related Cases
Go Pro!orto acess these features and extra content.
Ask Etalia.ai
Go Pro!orto acess these features and extra content.
Audio of Oral Arguments
Free Trial!
Become a Sponsor

Support Us
Copyright © 2026Etalia.ai All Rights Reserved
  • Blog
  • •
  • Privacy
  • •
  • Terms