The case involved a dispute between Pacific Gas & Electric Co. (PG&E) and Sierra Pacific Power Co. over the interpretation of a contract for the sale of electricity. The central issue was whether PG&E could unilaterally increase rates charged to Sierra under their agreement, which had been approved by the Federal Power Commission (FPC). PG&E argued that changing circumstances justified an adjustment in rates, while Sierra contended that any modification required FPC approval due to public interest considerations embedded within federal regulations governing interstate energy transactions. The Supreme Court held that rate changes must be filed with and approved by the FPC before they can take effect, emphasizing regulatory oversight designed to protect consumers from unjust or unreasonable charges.

Opinion written by Justice Harlan(2)

Decided 27 Feb 1956 · Official report